The Port Authority has approved plans to replace the 1973 central plant serving Terminals A, B and C and sought market interest.

image

Newark Liberty heating and refrigeration plant replacement

Credit: Port Authority of New York and New Jersey

The Board of Commissioners for the Port Authority of New York and New Jersey has approved a request to advance plans to replace the central heating and refrigeration plant serving Terminals A, B and C at Newark Liberty International Airport (EWR).

The new plant is expected to be a foundational component of the airport’s modernisation, providing heating, cooling and potentially power to more than 5 million square feet of existing and future passenger terminal space. The work may include planning for phased construction at operating facilities, as well as expenses linked to the procurement of construction awards.

Market feedback sought on delivery model

Alongside the Board’s authorisation, the Port Authority has released a Request for Expressions of Interest (RFEOI) for delivery of the new plant. The nonbinding RFEOI is intended to identify firms interested in the future procurement process and gather market feedback to inform the agency’s approach. Feedback is sought on commercial structure, technical delivery, phasing, performance management, decarbonisation and future proofing.

The Port Authority is particularly interested in hearing from infrastructure equity investors, developers, energy-as-a-service providers, operators, financial institutions, designers and builders with experience delivering complex energy and aviation infrastructure.

Under the proposed commercial framework, the selected developer would be expected to design, build, finance, operate and maintain the new facility and its associated energy distribution infrastructure. The developer would also work with airport energy users, including terminal operators, airlines and other tenants, and potentially enter into agreements with them. The agency intends to follow the process with a competitive procurement.

The existing plant was built in 1973 and is approaching the end of its useful life. Its current location cannot accommodate the larger facility needed to serve the new and expanded terminals included in the Port Authority’s EWR Vision Plan. The 2026-2035 Capital Plan includes funds for the replacement.

The project is expected to be delivered in phases while maintaining passenger service to all terminals. The facility is also expected to incorporate sustainability measures aligned with the Port Authority’s net-zero roadmap.

Port Authority Executive Director Kathryn Garcia said: “This request for expressions of interest from eligible firms helps us turn the EWR Vision Plan into reality. We are preparing the industry and market for potential partners to build a brand-new Newark Liberty. This is an invitation to invest in not just Newark Airport, but in New Jersey itself.”

The replacement forms part of the airport’s wider transformation, which began with the opening of Terminal A in 2023. The terminal went on to win the 2024 World’s Best New Airport Terminal award and a five-star rating from Skytrax. A new AirTrain Newark is under construction, planning and design work is under way for a new Terminal B, and a new entry point to the airport’s rail station is being built.

Port Authority Chairman Kevin O’Toole said: “We have begun the generational transformation of Newark Liberty through our investments so far that will reshape the airport for millions of travellers and visitors to our region.”

Responses to the RFEOI are due by 10 December 2026.